Astro PFP FR Acrylic - Fire Rated Mastic
Designed to prevent the spread of fire and smoke through joints and openings in fire rated walls and floors (including openings formed around building service penetrations); the Astro PFP FR Acrylic will also maintain the acoustic design performance.
When subjected to atmospheric conditions, the sealant cures however, it will retain a degree of elasticity for joint movement. Under fire exposure, The Astro PFP FR Acrylic creates a robust fire seal by the formation of a durable intumescent char.
The Astro PFP FR Acrylic can be used with a suitable filling material i.e. stone wool or Astro PFP FR backing material in order to secure correct width to depth ratio, and to reduce the shrinking of the sealant during curing. Minimum depth and maximum width of the joints are included in the installation instructions.
When testing pipes, one can choose not to cap (or close) the pipe, or cap the pipe inside the furnace, or outside the furnace, or on both sides. The configuration chosen depends on the intended application of the pipe and/or the installation environment.
The code defining if a pipe is capped is stated after the fire classification. For instance, EI 60 C/U which means the pipe was capped inside the furnace, and uncapped outside the furnace. The test configuration defines the approvals possible.
Our engineering judgment based on EN 1366-3:2009 are:
Intended use of pipe | Pipe end condition4 | |
Rainwater pipe, plastic | At drainage | U/U1) |
Not at drainage | C/C2) | |
Drainage or sewage pipe, plastic | Ventilated drain | U/U1) |
Unventilated drain | U/C1) | |
Drain w/water trap | U/C1) | |
Not at drainage | C/C2) | |
Pipe in closed circuit (water, gas, air, electricity etc.) | C/C2) 3) | |
Flue gas recovery system pipe, plastic | U/C1) | |
Pipe with open ends and ≥ 50cm length on both sides, plastic | U/U2) | |
Pipe supported by suspension system, metal | Fire rated support | C/U1) |
Non-fire rated | U/C1) | |
Waste disposal shaft pipe, metal | U/C1) |
1) Suggested in EN 1366-3:2009. 2) Astroflames's judgment based on tests. 3) Metal pipes should have fire rated support. 4) U/U classified fire seals cover C/U, U/C and C/C. C/U classified fire seals cover U/C and C/C. U/C classified fire seals cover C/C.
Technical Data
Condition | Ready for use, acrylic based filler |
Specific gravity | 1.56 - 1.60. |
Flash point | None |
Reaction to fire | B - S1, d0 |
Expansion in fire | 1 : 2-3 |
Non-sticky | Max. 75 minutes |
Film forming | Max. 25 minutes |
Totally hardened | 3 to 5 days depending on thickness and temperature |
Flexibility | 12.5% in mortar/concrete/masonry EN ISO 9046 |
Durability | Z2 intended for use in internal conditions with humidity classes other than Z1, excluding temperatures below 0°C |
BWR 3 | Use category IA1, S/W3 |
Thermal conduct. | 0.845 W/mK (+/- 3%) @ 20mm depth |
Storage | 24 months stored in unopened cartridges. To be stored in temperatures between 10°C and 30°C |
Service temp. | -20 to +70°C |
Application temp. | +5 to +30°C |
Compatibility | Suitable for use with most materials, but should not be used In direct contact with bituminous materials |
Limitations | Should not be used in permanently damp areas or in joints with high movement |
Classification | CE-marked - Sealant for fire rated joints and penetrations class EI 240 |
Standard colours | Standard white |
Colour codes | White: RAL 9002 |
This Technical Data Sheet and the Installation Instructions are based on the product's European Technical Assessment issued in accordance with regulation (EU) No 305/2011 on the basis of EAD 350454-00-1104 and EAD 350141-00-1106.
Product Availability
Product Code | Product Description | Colour | Size |
AFPFPACW | Astro PFP FR Acrylic - Cartridges | White | 310 ml |
AFPFPACW/FOIL | Astro PFP FR Acrylic - Foil | White | 600 ml |
Installation
We have technical representatives who provide assistance in the selection and specification of the products on this site and should be consulted for exact installation and product suitability. Ensure an early engagement with ourselves, designers, main contractor and specialist installers before any installation. Other trades and/or manufacturers may need to be consulted.
Maintenance
All interested parties, designer, specifier, main contractor and specialist installers should provide access to allow the fire stopping seals to be regularly inspected and maintained, as well as records kept of such maintenance at minimum periods of 12 months, as required by the Regulatory Reform Order, and repaired if necessary. Reference should be made to ASFP TGD 17 – Code of Practice for the Installation and Inspection of Fire Stopping.
Competency
It is vital that those entrusted to design or install a fire stopping product have the necessary levels of competence to undertake the task professionally and thoroughly. The level of competency required will be commensurate with the expected complexity of the building. All designers must eliminate, reduce or control foreseeable risks that may arise during installation, construction or maintenance when preparing or modifying designs. Clients should ensure that the principal designer and principal contractor carry out their duties under CDM regulations. The ASFP foundation course in passive fire protection provides essential knowledge as part of demonstrating competency and understanding in this key fire protection specialism.